Wauleco Paving Improvement Project
In line with ongoing site improvements, Wauleco will upgrade the existing chipseal paving at our site. The work is slated to begin on October 30, with a completion target of mid-November 2023.
As shown on this map, Wauleco will be installing an asphalt drive where the current drives are located. The remainder of the site will be covered with approximately 4-inches of ¾-inch washed stone, except within the two existing stormwater retention basins.
The project will require bringing in a significant volume of new materials to the site. We estimate more than 300 one-way truck trips over the project’s duration.
To mitigate dust during the project, we’ll be enacting several dust control Best Management Practices. A water truck and specialized dust control equipment will be on-site throughout the project.
Residents along River, Emter, and East Thomas streets near the site should have received a post card notifying them of this work.
Well Redevelopment and Carbon Changeout
To keep our treatment system operating smoothly, we periodically perform routine operation and maintenance (O&M) tasks. For reference, please see the treatment system flow illustration on the remediation page.
In spring 2021, we executed the following O&M tasks:
Well redevelopment: At select extraction wells, we cleaned the well screens to help improve pumping efficiency. Because this was an outdoor process, you may have noticed additional equipment onsite.
Carbon changeout: Some of the tanks in our interior treatment system contain granular activated carbon (GAC). We removed this carbon from select tanks and replaced it with regenerated carbon. We then shipped the removed carbon off-site for regeneration. Once it was regenerated, it was returned to us for future use—a key element of our sustainability measures. With the exception of a transport vehicle parked near the facility, this was an indoor process.
We worked with experienced contractors for both O&M tasks. These contractors provided specialized equipment that allowed us to perform these processes safely and efficiently.
Final Results Are In: Soil Samples Associated With Wauleco's Past Wood Burning Activities Show Dioxin Levels Well Within State Standards
WAUSAU, Wis.—In a final site investigation report concerning past wood burning which was submitted by Wauleco, Inc. to the Wisconsin Department of Natural Resources (WDNR) today, it was concluded that historic wood waste burning practices by the company did not generate contaminants that exceeded state standards.
Sampling was requested by the WDNR earlier this year to determine if soil near Wauleco’s site at 125 E. Rosecrans in Wausau contained dioxins resulting from wood waste burning that was curtailed nearly 50 years ago. Wauleco’s internal review of historical records revealed that most of the wood burned was kiln-dried lumber and shavings/sawdust that was not surface coated with wood preservatives. Burning untreated wood would have resulted in fewer products of incomplete combustion, such as dioxins. Wauleco’s review of internal documents also confirmed that the WDNR was aware of Wauleco’s use of wood to fuel one of its boilers and issued a permit covering the operation.
In addition to Wauleco, the WDNR has made similar requests for information from three other entities in the neighborhood that also operated incinerators or smokestacks at a time when it was standard practice.
The WDNR approved Wauleco’s work plan for soil sampling in May. The 36 locations chosen for the sampling were based on Wauleco’s wind dispersal analysis, which allowed the company to target the areas that would most likely have been affected by its historic wood waste burning activities. Ten of the 36 samples were collected from these areas. However, because dioxins can be found throughout the environment and can come from numerous sources, additional sample areas outside the target areas were recommended by Wauleco, and approved by the WDNR, to identify “background” conditions, meaning conditions that exist regardless of Wauleco’s wood waste burning. Five of these background samples exceeded state standards, though all five are not attributable to Wauleco’s wood burning. Those samples include the railroad corridor, vehicular traffic, and other areas that would typically be potential locations of backyard burning activities.
State toxicologists previously concluded that there is no apparent health hazard at Riverside Park and in the Thomas Street area based on the results of soil samples taken previously by others, but also recommended additional sampling be performed. The City has indicated it will ask those same state health experts to analyze this new data.
The final report, as submitted on October 29, 2019, along with additional information on Wauleco’s environmental clean-up efforts, can be found here.
Remediation
Over the past three decades, our onsite remediation system has successfully recovered and removed contaminants from beneath the Wauleco site. We’ve provided an overview of our remediation efforts here.
Reports
We’ve worked with industry-leading experts from the WDNR and other researchers to assess our cleanup efforts. You can access and review the complete reports and other communications here.
Timeline
To gain a complete understanding of our current and future environmental cleanup efforts, it’s important to know how we got here. This timeline highlights key moments in the history of the Wauleco property.
We recognize the complexity of this topic, and we’re dedicated to delivering the information you need. That’s why we’ve compiled several frequently asked questions and provided thorough answers.